Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

HTML
headtrue
script#http://www.ing.iac.es/weave/scienceHomePage/weave_header.html
 
HTML
script#http://www.ing.iac.es/weave/scienceHomePage/ConfigureConfluencePage.html
 

Removal of the WHT Flip Ring

Align

The top end of the 4.2-m William Herschel Telescope (WHT) consists of an outer fixed ring, which is supported by eight Serrurier trusses, and an inner flip ring.  The flip ring is attached to the outer ring such that it is allowed to rotate around an axis that allows it to be flipped through 180o.  This flipping procedure permits the telescope to be configured with a secondary mirror or with an instrument at prime focus (see Figure 1).

Align
aligncenter

Figure 1: The WHT top end showing the flip ring inside the fixed ring.  The configuration is such that the secondary mirror, which is covered, is facing the primary mirror.
Align

The WEAVE top-end assembly requires that this inner ring, along with the vanes and the prime focus corrector, is removed; an activity that had never been attempted in the history of the telescope.  Prior to removal, an alignment telescope, positioned in the Nasmyth focal station, was used to record the position of the secondary mirror with respect to a reference mark within the alignment telescope (see Figure 2). 

Align
aligncenter

 

Figure 2: A collimated green beam was propagated through the crosshair of the alignment telescope, reflected off the secondary mirror and its position, with respect to a circular reference mark on the mirror, was recorded. 
Align

ING astronomers then carried out a Shack-Hartmann analysis to characterise the combined optical quality of the primary and secondary mirrors.  The results of this analysis can be seen in Table 1.

Align
aligncenter

Elevation (o)

Raw image

RMS

Raw image

80%

Sub

Sub

RMS

Sph

RMS

Coma

RMS  

Coma

extent

Astig

RMS

Coma

PA

80

0.15

0.52

0.42

0.11

0.01

0.04

0.27

0.08

152

48

0.11

0.40

0.29

0.08

0.00

0.06

0.36

0.05

176

37

0.10

0.38

0.31

0.08

0.01

0.04

0.23

0.05

-164

23

0.11

0.41

0.28

0.08

0.01

0.07

0.44

0.03

177

 

Table 1: The Shack-Hartmann test results, in arcsec, prior to removing the ring.  For more information see the WHT optics log.
Align

The following day, on the 19th of July 2016, ING engineering staff successfully removed the 5.5-tonne flip ring by separating the two bearing housings of the ring from its interface to the outer fixed ring (see Figure 3).

Align
aligncenter

 

Figure 3: The left-hand bearing, with the dowel pins (only one shown in picture) removed, showed no movement of the bearing housing with respect to the outer ring.  After removing the four bolts, a small movement (80µm) to the left of the bearing housing was seen.  Before continuing with the process, it was confirmed that this displacement could be recovered.
Align

The WHT 25-tonne crane, with a series of lifting strops, was used to lift the flip ring (Figure 4). The crane, which is supported from the dome, has a limited patrol range but was proven to be sufficient to allow the rings to be separated.

Align
aligncenter

 

Figure 4: The flip ring is lifted using the WHT 25-T crane.
Align

Figure 5 shows a series of photographs that were taken at the moment that the two rings were separated.

Align
aligncenter

Borderless table

The bearings are unbolted and separated from the fixed ring.

The flip ring is moved up and outwards.
The ring is completely detached.

Due to the travel limitations of the crane, the ring cannot be moved further to the right.

Figure 5: Images showing the moment when the flip ring was separated from the fixed ring.
 

 

Align

Although the task was well-planned, there were a couple of issues that had to be addressed as the activity progressed and these did produce some sweat but thankfully no blood (see Figure 6). 

Align
aligncenter

Figure 6: The ring clears a support bracket, on the fixed ring, by millimetres leaving the Head of the Mechanical Section somewhat apprehensive.
Align

Once the ring was separated from the fixed ring, it was manoeuvred above GHRIL and lowered to the ground floor (see Figure 7).  This was a delicate and slow operation which took about 30 minutes.

Align
aligncenter

 

 

Borderless table
Figure 7: The ring is lifted over GHRIL (left) and lowered to the ground floor (right).

Align

The flip ring was stored overnight in a purpose-built trolley, constructed by SENER and provided by the Instituto de Astrofísica de Canarias (IAC) as part of its contribution to the WEAVE project (see Figure 8).

Align
aligncenter

Figure 8: Whilst WEAVE is on the telescope, the flip ring is stored in its trolley on the ground floor of the telescope building.
Align

Figure 9 shows the WHT without the flip ring.  In this configuration, the telescope was out of balance by 5.5T but was held in position by a 7-T load which was placed on the ground floor and attached to the blue strops.  A secondary restraining system, achieved by securing the fixed ring to the telescope support structure, was also implemented.

Align
aligncenter

 

 

Figure 9: The WHT top end without the flip ring.  Movement of the telescope in elevation is restricted using a restraining system.
Align

On the 20th of July, the process to replace the flip ring was initiated and four hours later the ring was back on the telescope.  The remainder of the day was dedicated to adjusting the ring to its original position, recabling and replacing the items that had to be detached to allow the flip ring to be removed.  On the 21st, the telescope was balanced and the test using the alignment telescope was repeated (see Figure 10).  This test showed no discernible differences when compared with the results of the test that was carried out prior to removing the ring.

Align
aligncenter
Figure 10: A collimated green beam was propagated through the crosshair of the alignment telescope, reflected off the secondary mirror and its position, with respect to a circular reference mark on the mirror, was recorded. 
Align

During the night of the 21st, the astronomers repeated the Shack-Hartmann analysis and concluded that there was no significant change in the optical quality of the telescope (see Table 2). Interestingly, there was a reduction in the amount of coma observed.

Align
aligncenter

 

 

Elevation (o)

Raw image

RMS

Raw image

80%

Sub

Sub

RMS

Sph

RMS

Coma

RMS  

Coma

extent

Astig

RMS

Coma

PA

80

0.11

0.38

0.34

0.09

0.00

0.03

0.14

0.05

168

59

0.11

0.41

0.32

0.09

0.01

0.03

0.15

0.06

170

31

0.11

0.31

0.30

0.09

0.01

0.06

0.34

0.05

157 

27

0.10

0.35 

0.29

0.08 

0.02

0.04

0.25

0.04 

171

 

Table 2: The Shack-Hartmann test results, in arcsec, after the ring was replaced.  For more information see the WHT optics log.
Align

The telescope is now fully operational and a plan of additional work is being proposed to simplify the removal process.  This marks a significant milestone in ING's preparations to receive WEAVE.  The current expectation is that this procedure will need to be carried out once per semester with the removal taking less than seven hours to complete.

 

 

 

Borderless table
Profile picture
Userdon
HTML
Don Carlos Abrams
<BR>
Head of Engineering
<BR><BR>
23<sup>rd</sup> July 2016